Lidcombe Railway Bridge Upgrade

Antoun Civil were engaged by RailCorp (formerly Sydney Trains) for the construction of concrete bridge piers under an existing steel trestle railway bridge. The concrete piers were placed prior to a weekend railway shut down when the existing steel deck frame was to be replaced by a new concrete plank deck.
The concrete and steel works were placed in accordance with RMS specification B80.

Due to the construction of the piers being located in the centre island of a multi lane arterial road, all of the works were performed at night under road occupancy and lane closures.
Traffic control for the works was also performed by Antoun Civil Engineering.

Client

RailCorp

Location

Olympic Drive, Lidcombe NSW

Contract Value

$1 million – $5 million

Duration

20 weeks